Scrum Scaled Professional Scrum (SPS) Exam SPS Question # 7 Topic 1 Discussion

Scrum Scaled Professional Scrum (SPS) Exam SPS Question # 7 Topic 1 Discussion

SPS Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

The Scrum Teams in a Nexus find they have simply too much work each Sprint to do to deliver

a valuable and useful Increment. What could they try to improve their ability to produce an

Increment for the next Sprint?

(choose the best answer)


A.

Reduce the amount of work that the teams pull into the Sprint.


B.

Ask the Nexus Integration Team to extend the Sprint to allow more time for

integration.


C.

Reduce the number of Scrum Teams to reduce complexity.


D.

Add another Scrum Team to the Nexus to increase capacity.