Question #: 26
Topic #: 3

Which of the following statements are NOT true about a Scrumboard?

I. A Scrumboard can be maintained manually on paper or a whiteboard.

II. A Scrumboard is used by the stakeholders to plan and track progress during each Sprint.

III. A Scrumboard can contain three or four columns to indicate the progress of estimated tasks for the Sprint.

IV. A Scrumboard is created during the Create Deliverables process.


A.

I and II


B.

II


C.

III and IV


D.

II and III