Risk is explicitly one of the principal factors considered when constructing and prioritizing the Prioritized Product Backlog. SCRUMstudy identifies value, risk or uncertainty, and dependencies as three primary factors on which backlog prioritization is based.
Option A is therefore incorrect because dependencies may materially affect sequencing. One User Story may rely on functionality supplied by another, and such relationships must be considered during prioritization. SCRUMstudy also identifies splitting or combining stories as possible approaches for resolving dependencies.
Option B is too restrictive. Business value is important, but prioritization is not based only on subjective value. Risk, dependencies, business requirements, estimates, and other relevant considerations influence the ordering of work.
Option D is also incorrect because Scrum can use multiple prioritization techniques, including collaborative methods where appropriate. The framework does not establish a universal prohibition on voting.
Risk-aware prioritization allows high-risk or high-uncertainty work to be addressed early enough to expose problems and enable mitigation.
Study Guide reference: Business Justification - > Value-based Prioritization; Risk - > Risk-adjusted Prioritized Product Backlog.
========