Scrum Master Certified (SMC) SMC Question # 20 Topic 3 Discussion

Scrum Master Certified (SMC) SMC Question # 20 Topic 3 Discussion

SMC Exam Topic 3 Question 20 Discussion:
Question #: 20
Topic #: 3

While performing a cost-benefit analysis, the Product Owner of a project determined that the project has 45% probability of incurring a loss of $800,000 due to the latest Land Reform Bill. Which of the following techniques is being used by the Product Owner to perform cost-benefit analysis?


A.

Expected Monetary Value.


B.

Probability Impact Grid.


C.

Pareto Analysis.


D.

Risk Breakdown Structure.