Black Friday Reward - Upto 75% off - Ends in 0d 00h 00m 00s - Coupon code: CFsave75

Scrum Master Certified (SMC) SMC Question # 11 Topic 2 Discussion

Scrum Master Certified (SMC) SMC Question # 11 Topic 2 Discussion

SMC Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2

Which of the following is true with respect to maintaining stability in a Scrum project?


A.

The Scrum Master and the Scrum Team should ensure non-interference or changes during a Sprint.


B.

The Sponsor should allow creation of Change Requests and approve them to be incorporated during the ongoing Sprint to avoid unexpected rework later.


C.

The Scrum Team should ensure that complete stability is obtained with the help of iterative delivery and other Scrum characteristics and principles.


D.

Any kind of Change Request can be approved only by the Product Owner.


Get Premium SMC Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.