Question #: 18
Topic #: 2

If a team insists that big Stories cannot be split into smaller ones, how would the Scrum Master coach them to do otherwise?


A.

Emphasize the SAFe principles to highlight the importance of flow


B.

Suggest a story-splittingbootcamp in the next IP iteration


C.

Demonstrate Story-splitting techniques using a specific example


D.

Invite a development manager to emphasize the importance of splitting Stories