Scrum Professional Scrum Product Owner (PSPO I) Exam PSPO-I Question # 51 Topic 6 Discussion

Scrum Professional Scrum Product Owner (PSPO I) Exam PSPO-I Question # 51 Topic 6 Discussion

PSPO-I Exam Topic 6 Question 51 Discussion:
Question #: 51
Topic #: 6

Which of the following is required by Scrum?

(choose the best answer)


A.

Sprint Retrospective.


B.

Developers must stand up at the Daily Scrum.


C.

Sprint Burndown Chart.


D.

Release Planning.


E.

All of the above.