Scrum Professional Scrum Product Owner (PSPO I) Exam PSPO-I Question # 37 Topic 4 Discussion

Scrum Professional Scrum Product Owner (PSPO I) Exam PSPO-I Question # 37 Topic 4 Discussion

PSPO-I Exam Topic 4 Question 37 Discussion:
Question #: 37
Topic #: 4

True or False: All planned work for the Product done by the Scrum Team must originate from the Product Backlog.


A.

True


B.

False


Get Premium PSPO-I Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.