What activities would a Product Owner typically undertake in the period between the end of the

current Sprint and the start of the next Sprint?

(choose the best answer)


A.

There are no such activities. The next Sprint starts immediately after the currentSprint.


B.

Refine the Product Backlog.


C.

Update the project plan with stakeholders.


D.

Work with the Quality Assurance departments on the Increment of the current Sprint.