Scrum Professional Scrum Master I PSM-I Question # 62 Topic 7 Discussion

Scrum Professional Scrum Master I PSM-I Question # 62 Topic 7 Discussion

PSM-I Exam Topic 7 Question 62 Discussion:
Question #: 62
Topic #: 7

What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?


A.

There are no such activities. The next Sprint starts immediately after the current Sprint.


B.

Refine the Product Backlog.


C.

Work with the Quality Assurance departments on the Increment of the current Sprint.


D.

Update the project plan with stakeholders.


Get Premium PSM-I Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.