The correct answers are A and B, because these are true about the Product Owner role. The Product Owner is one person, not a committee or a team, who is accountable for ordering the Product Backlog and maximizing the value of the product. The Scrum Guide states that “the Product Owner is responsible for maximizing the value of the product resulting from work of the Development Team. How this is done may vary widely across organizations, Scrum Teams, and individuals. … For the Product Owner to succeed, the entire organization must respect his or her decisions.”