Scrum Professional Scrum Developer 1 (PSD I) PSD Question # 33 Topic 4 Discussion

Scrum Professional Scrum Developer 1 (PSD I) PSD Question # 33 Topic 4 Discussion

PSD Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

Which statement best describes the sprint review?


A.

It is a chance for inspecting the outcome of a sprint and determining the next steps


B.

It is a mechanism to control the work of the developers


C.

It is a demo of the work that was done