Question #: 29
Topic #: 3

How do you know that a Scrum Team is cross-functional? (choose the best answer)


A.

The Scrum Team has all the skills to create an Increment by the end of every Sprint.


B.

Every member of the Scrum Team is able to perform every task.


C.

There are no conflicts within the Scrum Team.


D.

A few of the Developers pair program and do Test-Driven Development.