Based on "Sprint 7 Burn-Down Chart," would you do anything different in Sprint 8? (choose the best two answers)
A.
The Developers may forecast less overall work in Sprint 8.
B.
Stakeholders will encourage the Scrum Team to estimate better during the Sprint 8 Planning Meeting.
C.
There is nothing wrong. The Developers will present all Product Backlog items selected for Sprint 7 at the end of the Sprint.
D.
The Developers carry over incomplete Sprint Backlog items from Sprint 7 to Sprint 8 and monitor the Sprint 8 burn-down chart. As soon as deviation from trends is detected, the Developers work with the Product Owner to negotiate remaining work.
E.
The Scrum Master adds additional Developers for Sprint 8.
F.
The Developers put incomplete Product Backlog items back into the Product Backlog for re-ordering. The Product Owner may ask the Developers to complete the unfinished Product Backlog items from Sprint 7 in Sprint 8.
Detailed Explanation: If a burn-down chart shows issues in Sprint 7, the Developers may adjust the forecast for Sprint 8 based on learning. Incomplete items should be returned to the Product Backlog for reordering, ensuring prioritization aligns with goals.