Scrum Professional Scrum Developer 1 (PSD I) PSD Question # 23 Topic 3 Discussion

Scrum Professional Scrum Developer 1 (PSD I) PSD Question # 23 Topic 3 Discussion

PSD Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3

True or False: A high-performance Scrum Team ensures that each Increment is complete by running a Release Sprint.


A.

True


B.

False