Scaled Agile SSM (6.0) - SAFe Scrum Master SSM Question # 11 Topic 2 Discussion

Scaled Agile SSM (6.0) - SAFe Scrum Master SSM Question # 11 Topic 2 Discussion

SSM Exam Topic 2 Question 11 Discussion:
Question #: 11
Topic #: 2

What is the intended value of the Backlog Refinement event?


A.

The team is able to prepare requirements for Iteration Planning


B.

The team aligns on the progress of Iteration Goals


C.

The team is able to commit to a set of goals to be delivered in the Iteration


D.

The team reviews and improves processes before the next Iteration