The System Demo is the only true objective measure of an Agile Release Train (ART) within the SAFe framework. It is a significant event that occurs at the end of each Iteration where the current state of the Solution is demonstrated to stakeholders. This event reflects the integrated efforts of all the teams on the ART and provides a clear, objective measure of progress1.
The System Demo serves several critical purposes:
It provides a regular, objective assessment of the solution’s evolving functionality.
It offers a platform for feedback from stakeholders, which is vital for the iterative improvement of the solution.
It fosters transparency and alignment among teams and stakeholders.
By showcasing the working system, the demo ensures that everyone has a shared understanding of what has been accomplished and what is still in progress. This aligns with the SAFe principle of transparency and enables informed decision-making based on the actual state of the solution1.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit