CVS Exam Topic 5 Question 43 Discussion:
Question #: 43
Topic #: 5
The project team expresses uncertainty about how their tasks align with the overall objectives of the VM Job Plan. What steps should the VM facilitator take to enhance understanding of the VM Job Plan?
Choose 2 answers.
A.
Encourage a collaborative environment by pairing project and VM team members for more in-depth discussions of each other’s roles.
B.
Facilitate a discussion to improve their understanding of how their tasks contribute to the VM Job Plan.
C.
Present the VM Job Plan in detail with minimal interaction, allowing team members to ask questions at the end.
D.
Establish a deadline for project members to complete their preparation.
The correct answers are A and B . The issue in the scenario is not lack of a deadline; it is lack of shared understanding of how individual responsibilities support the VM Job Plan. SAVE describes Value Methodology as a multidisciplinary team process used to improve project value through function analysis, and the VM Standard requires the Value Study Team to include experienced professionals and project stakeholders selected for their expertise and project experience. Therefore, pairing project and VM team members for deeper role discussion is appropriate because it builds cross-functional understanding, clarifies responsibilities, and improves team integration.
Option B is also correct because the facilitator should actively guide discussion so team members understand how their tasks contribute to the structured Job Plan. SAVE’s Study Guide states that the Job Plan supports team synergy within a structured process rather than a collection of individual opinions, and each phase provides information and understanding needed for the next phase. SAVE’s glossary also defines a facilitator as a substantively neutral person who enables the group to improve problem solving, decision making, and effectiveness while leading the group through the VM Job Plan.
Option C is weaker because a low-interaction lecture does not address uncertainty effectively. Option D manages schedule compliance, not understanding or alignment.
References/topics: VM Facilitation; Team Dynamics; VM Job Plan; Multidisciplinary Team; Facilitator Role.