The correct answers are B, D, and E . An Implementation Form is used after VM proposals have been developed, presented, reviewed, and moved into disposition or execution tracking. Its purpose is to identify each accepted or pending value alternative clearly enough that management, the project team, and follow-up reviewers can track what proposal is being implemented, who developed or owns it, and how it will be handled.
The SAVE International Study Guide describes Implementation Activities as ensuring accepted value alternatives are implemented and that projected benefits are realized. It further identifies activities such as conducting an implementation meeting, determining the disposition of each value alternative, establishing action plans, obtaining commitments, setting timeframes, tracking value achievement, and validating benefits. ( )
Therefore, an implementation form normally requires traceable proposal identifiers: the VM proposal number , the title of the VM proposal , and the developer or originator/responsible party . These fields allow each proposal to be tracked from study recommendation through acceptance, rejection, modification, and completion. A creative idea list belongs to the Creativity Phase record, not implementation tracking. Risk impacts may support development or recommendation documentation, but they are not as fundamental as proposal identity and responsibility fields on the implementation form.
References/topics: Implementation Phase; VM Proposal Tracking; Action Plans; Follow-Up; Value Study Recommendation Documentation.
Submit