The correct answers are B and C . In the VM Job Plan, implementation support requires more than approving an idea; it requires a controlled plan for turning accepted VM proposals into real changes. SAVE’s Value Methodology Standard identifies Create Implementation Plan and Prepare Final Proposals as Development Phase activities, followed by Presentation Phase commitment and Post-Study implementation tracking. ( UW Courses )
A detailed implementation plan is essential because the standard specifically requires an implementation plan with a proposed schedule, implementation activities, team assignments, and management requirements. ( UW Courses ) This directly supports option B . A contingency plan is also appropriate because implementation must account for risk, uncertainty, schedule impact, resource availability, policy limits, and potential barriers. The Development Phase includes implementation requirements that consider risk and uncertainty, making contingency planning a logical implementation-control tool. ( UW Courses )
Option A may be useful background information, but it is not the primary tool for implementing approved proposals. Option D is incorrect because implementation should not proceed blindly without assessing current policies, procedures, constraints, and organizational requirements.
References/topics: Implementation Phase; Development Phase; Implementation Plan; Risk and Uncertainty; Post-Study Implementation.
Submit