The correct answers are A, B, and C . An implementation plan for accepted VM proposals must translate approved recommendations into executable action. Therefore, it must identify the implementation costs , the responsible parties , and the schedule for completing the required activities. The SAVE Value Methodology Standard states that during proposal development, the team prepares implementation requirements, including estimated initial costs, life-cycle costs, and implementation costs , while accounting for risk and uncertainty. It also requires technical data to identify schedule impact. ( UW Courses )
The same Standard further specifies that the implementation plan should include the proposed schedule of all implementation activities, team assignments, and management requirements. This directly supports responsibility and schedule as required plan elements. ( UW Courses ) In the Implementation/Post-Study activity, assignments may be made to VM team members or to other individuals designated by management, so the key requirement is not generic “VM Team involvement” but clear accountability. ( UW Courses ) “New proposals” are not part of the implementation plan for already accepted proposals; they would belong to a new study cycle or further development.
References/topics: Implementation Phase; Development Phase; Implementation Plan; Accepted VM Proposals; Responsibility Assignment; Schedule and Cost Requirements.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit