What information does the Scrum team need before they can correctly estimate the relative size of backlog user stories? Note: There are 2 correct ans-wers to this que-stion.
Before the Scrum team can correctly estimate the relative size of backlog user stories, they need specific information that includes:
A. Definition of Done: This clarifies what criteria must be met for the user stories to be considered complete. Understanding the Definition of Done helps the team accurately estimate the effort required to fulfill these criteria.
D. Definition of Ready: This ensures that user stories are adequately prepared and meet all necessary conditions for the team to start work on them. A clear Definition of Ready helps in determining if the story is actionable and estimable.
Both the Definition of Done and the Definition of Ready provide critical context that impacts how the team evaluates the work and complexity involved, ensuring more accurate and consistent estimations.References: