What are key goals of the burndown chart? Note: There are 2 correct ans-wers to this que-stion.


A.

Determination of the overall availability of the team for the future sprints


B.

Assignment of backlog items to future sprint up to completion of the release


C.

Visualization of the size of the backlog consumed so far


D.

Determination of the planned go-live date based on current velocity