SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 C_TPLM22_67 Question # 44 Topic 5 Discussion

SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 C_TPLM22_67 Question # 44 Topic 5 Discussion

C_TPLM22_67 Exam Topic 5 Question 44 Discussion:
Question #: 44
Topic #: 5

You use a WBS Project Structure with networks and maintenance orders. You want to Schedule both the networks and the maintenance orders. What do you consider? *


A.

The maintenance orders must be assigned to the budget profile as the project definition


B.

The maintenance orders must be assigned to WBS elements


C.

The maintenance orders must be assigned to the same plant as the networks


D.

The maintenance orders must be assigned as sub-networks