SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 C_TPLM22_67 Question # 41 Topic 5 Discussion

SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 C_TPLM22_67 Question # 41 Topic 5 Discussion

C_TPLM22_67 Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

Which of the following related to an activity stipulates the activity type and determines how an activity is handled during calculation, scheduling and capacity planning?

Please choose the correct answer.

Response:


A.

Control key


B.

Confirmation key


C.

Scheduling key


D.

Customizing key