Question #: 23
Topic #: 3

When using budgeting and active availability control, which business transactions affect the current budget?

There are 3 correct answers to this question.

Response:


A.

Cost element planning


B.

Original budget


C.

Revenues


D.

Transfers


E.

Supplements