SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 C_TPLM22_67 Question # 21 Topic 3 Discussion

SAP Certified Application Associate - SAP Project Systems with SAP ERP 6.0 EHP7 C_TPLM22_67 Question # 21 Topic 3 Discussion

C_TPLM22_67 Exam Topic 3 Question 21 Discussion:
Question #: 21
Topic #: 3

When using networks and activities, planned costs are automatically calculated based on the resource requirements identified for which of the following?

There are 2 correct answers to this question.

Response:


A.

Tasks


B.

WBS


C.

Activities


D.

Operations


Get Premium C_TPLM22_67 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.