SAP Certified Associate - Implementation Consultant - SAP SuccessFactors Recruiting: Candidate Experience C_THR84_2411 Question # 18 Topic 2 Discussion
C_THR84_2411 Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2
What are the recommended actions to be completed before the Career Site Builder (CSB) kickoff call? Note: There are 2 correct answers to this question.
A.
Finish the CSB Configuration Workbook.
B.
Develop the CSB project plan.
C.
Assist the customer to complete the Readiness Checklist.
Comprehensive and Detailed In-Depth Explanation:The CSB kickoff call sets the implementation stage, requiring pre-call preparation to ensure alignment. Let’s explore the recommended actions:
Option C (Assist the customer to complete the Readiness Checklist): Correct. The Readiness Checklist confirms prerequisites (e.g., provisioning access, branding assets, domain setup) are met.
SAP Documentation Excerpt: From theImplementation Handbook: “Before the CSB kickoff call, the consultant should assist the customer in completing the Readiness Checklist to verify that all foundational elements, such as system access and branding materials, are prepared.”
Reasoning: Without assets like a logo or confirmation of careers.bestrun.com provisioning, the call can’t proceed effectively. The consultant reviews the checklist (e.g., Admin Center > Readiness) with the customer, ensuring items like “SSL Certificate Ready” are checked.
Practical Example: For “Best Run,” the consultant helps the customer confirm provisioning on January 10, 2025, before the January 15 kickoff.
Option D (Review the statement of work (SOW)): Correct. The SOW defines scope, deliverables, and timelines, ensuring all parties are aligned.
SAP Documentation Excerpt: From theImplementation Handbook: “Reviewing the statement of work prior to the CSB kickoff call is recommended to align expectations on deliverables, timelines, and responsibilities between the consultant and customer.”
Reasoning: Reviewing the SOW (e.g., confirming 20 Category pages, one XML feed) avoids mid-project scope creep. The consultant annotates the document, highlighting key points for discussion.
Practical Example: For “Best Run,” the consultant reviews the SOW on January 12, noting the go-live date of March 1, 2025.
Option A (Finish the CSB Configuration Workbook): Incorrect. The workbook is populated post-kickoff with requirements gathered during the call.
Option B (Develop the CSB project plan): Incorrect. The project plan is drafted after the kickoff, based on discussed needs.
Why C, D: These proactive steps enable a productive kickoff, per SAP’s methodology. SAP’s pre-kickoff preparation supports C and D.References: SAP SuccessFactors Recruiting: Candidate Experience - Implementation Handbook (Pre-Kickoff Preparation).