SAP Certified Associate - Administrator - SAP Fieldglass Contingent Workforce Management C_TFG51_2405 Question # 6 Topic 1 Discussion

SAP Certified Associate - Administrator - SAP Fieldglass Contingent Workforce Management C_TFG51_2405 Question # 6 Topic 1 Discussion

C_TFG51_2405 Exam Topic 1 Question 6 Discussion:
Question #: 6
Topic #: 1

Why is it important to have at least one Task Code assigned to the Worker?


A.

To provide guidance on how to correctly submit time


B.

To generate Time Sheets with the correct rate


C.

To allow the Worker to submit time for approval


D.

To allow Worker activation in the application