In the Price for Request (1XF) Process, using the Manage Supplier Quotations SAP Fiori app, which follow-on documents can be created after awarding a quotation? Note: There are 2 correct answers to this question.
In thePrice for Request (1XF)process, after awarding a supplier quotation using theManage Supplier QuotationsSAP Fiori app, follow-on documents can be created to formalize the procurement process. Below is an explanation of the correct answers:
Purchase Contract (A):A purchase contract can be created as a follow-on document to establish long-term agreements with the supplier for recurring purchases based on the awarded quotation.
Purchase Order (D):A purchase order is the most common follow-on document, used to formally request the delivery of goods or services from the supplier based on the awarded quotation.
Purchase Requisition (B):Purchase requisitions are internal requests for procurement and are typically created before quotations are requested. They are not follow-on documents after awarding a quotation.
Scheduling Agreement (C):While scheduling agreements are similar to contracts, they are not typically created directly from awarded quotations in this process.
[References:SAP Help Portal:Manage Supplier Quotations App, SAP Best Practices Explorer:Price for Request Process, ]