The typical sequence of testing in the Realize phase begins with the String Test, followed by the Integration Test to validate cross-functional flows, and concludes with the User Acceptance Test (UAT) to confirm system readiness from an end-user perspective.References:SAP Activate, Realize Phase Testing Sequence, Test Types and Order