Questions # 1:

What tool would you use for managing project tasks and Solution Documentation when implementing SAP S/4HANA Cloud, public edition?

Options:

A.

SAP Cloud ALM


B.

SAP Signavio Process Navigator


C.

SAP Roadmap Viewer


D.

SAP Transformation Navigator


Questions # 2:

Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?

Options:

A.

Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity


B.

Relative effort estimate in Ideal Person Days that reflects the best estimate by the Project Team


C.

Product Owner's relative effort estimate that will be needed to implement and test the user story


D.

Detailed bottom-up effort estimate by the Product Owner that breaks up each story into short tasks


Questions # 3:

You are implementing SAP S/4HANA Cloud, public edition for your customer. How do you activate the pre-configuration?

Options:

A.

Via the SAP Contact Center


B.

Via the SAP Business Technology Platform


C.

Via the Central Business Configuration System


D.

Via the SAP Cloud ALM


Questions # 4:

You are defining the testing strategy for your project.

What would you include in a Scope of Integration test? Note: There are 2 correct answers to this question.

Options:

A.

The procedures for data migration


B.

The connectivity between database and application servers


C.

The functionality of end-to-end business processes


D.

The connectivity with other systems


Questions # 5:

Which accelerators support the fit-to-standard workshop in the Explore phase? Note: There are 2 correct answers to this question.

Options:

A.

Quality gate checklist and quality gate guide


B.

Business-Driven Configuration questionnaire


C.

Test plan document


D.

Requirements feature in SAP Cloud ALM


Questions # 6:

Which of the following is a key characteristic of the Agile project approach?

Options:

A.

Higher business involvement in the early phases


B.

Frequent and detailed release scheduling


C.

Iterative build with frequent inspections


D.

Frequent quality gates in each sprint


Questions # 7:

Which of the following best outlines the sequence of testing in the Realize phase?

Options:

A.

Data Migration

String Test

User Acceptance Test


B.

String Test

Integration Test

User Acceptance Test


C.

String Test

User Acceptance Test

Integration Test


D.

Integration Test

User Acceptance Test

String Test


Questions # 8:

What technique helps a Scrum team to prioritize a large, flat backlog? Note: There are 2 correct answers to this question.

Options:

A.

Splitting the backlog into epics


B.

MOSCOW prioritization


C.

A/B testing user stories


D.

User story mapping


Questions # 9:

Which of the following characteristics relate to the Focused Build for SAP Solution Manager Functionality? Note: There are 2 correct answers to this question.

Options:

A.

SAP delivers a standard solution without any additional coding required.


B.

SAP delivers a standard solution with its own separate license.


C.

SAP delivers all configuration values within your project.


D.

SAP delivers all knowledge required with the solution.


Questions # 10:

What is the preferred option to migrate to SAP S/4HANA Cloud, private edition while keeping most of the original processes and adding new configuration?

Options:

A.

Mix and Match


B.

System Conversion


C.

Shell Conversion


D.

New Implementation