SAP Certified Associate - Project Manager - SAP Activate C_ACT_2403 Question # 6 Topic 1 Discussion

SAP Certified Associate - Project Manager - SAP Activate C_ACT_2403 Question # 6 Topic 1 Discussion

C_ACT_2403 Exam Topic 1 Question 6 Discussion:
Question #: 6
Topic #: 1

Which of the following is a key characteristic of the Agile project approach?


A.

Higher business involvement in the early phases


B.

Frequent and detailed release scheduling


C.

Iterative build with frequent inspections


D.

Frequent quality gates in each sprint