SAP Certified Associate - Project Manager - SAP Activate C_ACT_2403 Question # 2 Topic 1 Discussion

SAP Certified Associate - Project Manager - SAP Activate C_ACT_2403 Question # 2 Topic 1 Discussion

C_ACT_2403 Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?


A.

Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity


B.

Relative effort estimate in Ideal Person Days that reflects the best estimate by the Project Team


C.

Product Owner's relative effort estimate that will be needed to implement and test the user story


D.

Detailed bottom-up effort estimate by the Product Owner that breaks up each story into short tasks