Question #: 67
Topic #: 7

A consultant is working on a Service Cloud implementation with a fixed budget and

timeline. Additional requirements were discovered early on that will result in the project exceeding

timeline and budget constraints.

What is the first step the consultant should take to address the issue?


A.

Incorporate the additional requirements to the project scope and continue with the original project schedule.


B.

Prepare a change order to account for the additional requirements and communicate the new project schedule.


C.

Document the gap in requirements and discuss the schedule and budget Impact with the project team.