To model international workforces in Salesforce Field Service, specific objects handle geography, time, and exceptions.
Option B is correct.
Service Territories:Used to define the geographical areas (Countries/Regions). Crucially, theTime Zoneis defined on the Service Territory record.
Operating Hours:Used to define the "Permitted Working Hours" (e.g., Mon-Fri, 9-5). These are assigned to the Service Territory or Service Territory Member.
Resource Absences:Used to model time off, such as public holidays or sick days, where the resource is unavailable. (Note: Holidays can also be linked directly to Operating Hours, but Resource Absences are the distinct records created on the Gantt).
Option A is incorrect because "Business Hours" is a Service Cloud (Support) object used for Case Entitlements, not Field Service scheduling. "Resource Capacity" is used for contractors (Capacity-Based Scheduling), not for defining standard working hours.