Pure Storage FlashBlade Certified Architect Professional (FBAP_002) Exam FBAP_002 Question # 20 Topic 3 Discussion
FBAP_002 Exam Topic 3 Question 20 Discussion:
Question #: 20
Topic #: 3
The customer reports that the end clients shown in the diagram are NOT completing jobs on time. Each client writes 300MB/s to the FlashBlade for 45 minutes every hour, and they run concurrently. What does the architect need to do?
A.
Increase the number of DataVIPs available to the clients.
B.
Add additional mount point on each client.
C.
Increase bandwidth between Switch A and the Router.
D.
Stagger the job start times between the clients. ***
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.