Question #: 19
Topic #: 2

A FlashBlade is designed with a properly implemented single 4x40Gb/s LAG.

During implementation, the architect is informed that the ISL on the uplink switches in broken. The customer has no budget to repair or replace it. What should the architect do?


A.

Divide the single LAG into one LAG per switch. ***


B.

Change out the 40Gb/s cable for breakout cable.


C.

Using the same LAG, create a second subnet and VIP.


D.

Remove all uplink from FM2.