PRINCE2 Practitioner Exam Prince2-Practitioner Question # 27 Topic 3 Discussion

PRINCE2 Practitioner Exam Prince2-Practitioner Question # 27 Topic 3 Discussion

Prince2-Practitioner Exam Topic 3 Question 27 Discussion:
Question #: 27
Topic #: 3

The project is approaching the end of stage 4 and all work will be completed as planned. The project manager is now preparing a plan for acceptance and the handover of the 'capability to provide health and safety training'.

Is this appropriate, and why?


A.

Yes, because a plan should be created to measure the number of courses carried out after project closure.


B.

Yes, because a separate closure stage plan should be created during stage 4.


C.

No, because closure activities should have been planned at the end of stage 3.


D.

No, because user acceptance of the project's products should have taken place throughout the project.


Get Premium Prince2-Practitioner Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.