PRINCE2 Practitioner Exam Prince2-Practitioner Question # 26 Topic 3 Discussion

PRINCE2 Practitioner Exam Prince2-Practitioner Question # 26 Topic 3 Discussion

Prince2-Practitioner Exam Topic 3 Question 26 Discussion:
Question #: 26
Topic #: 3

The project is approaching the end of stage 3, and stage 4 is being planned as part of the 'managing a stage boundary' process.

Which action should the project manager carry out as part of the 'update the project plan' activity?


A.

Include the actual time and cost of the work to prepare the 'marketing materials' in the project plan.


B.

Ensure that the team manager for the work package 'delivered pilot courses' is included as a resource.


C.

Update the project's business case to show any new key risks that have been identified.


D.

Include the tolerances for the work package 'delivered pilot courses' in the project plan.


Get Premium Prince2-Practitioner Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.