The result of the change derived from using the project's product is referred to as the 'outcome'. An outcome is the effect of the change, typically a new capability that the project's outputs enable within the organization. This differs from outputs (which are tangible deliverables of the project) and benefits (which are the measurable improvements resulting from an outcome).References: = PRINCE2® 7 Foundation handbook and online resources