According to the ‘continued business justification’ principle of PRINCE2®, if a project can no longer be justified — meaning it no longer meets its original or updated justification for a viable return on investment — the funds allocated to it should be returned to corporate, programme management, or the customer. This ensures that resources are not wasted on unjustifiable projects.References: = PRINCE2® 7 Foundation handbook and online resources