Prince2-Foundation Exam Topic 4 Question 32 Discussion:
Question #: 32
Topic #: 4

Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.


A.

change budget


B.

project budget


C.

project's cost tolerance


D.

project's risk tolerance