During the Managing a Stage Boundary process, the Project Plan is updated with the latest estimated costs and time for the upcoming stage. This ensures that the Project Plan reflects current expectations and planning realities as the project progresses. References: PRINCE2® Foundation Training Manual; PRINCE2® 2017 Foundation handbook.