Question #: 19
Topic #: 2

If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?


A.

Appointing the project board and producing the project brief


B.

Planning the initiation stage and appointing the project manager


C.

Producing the additional role descriptions and validating the project product description


D.

Verifying the project approach and capturing previous lessons