PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 18 Topic 2 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 18 Topic 2 Discussion

Prince2-Foundation Exam Topic 2 Question 18 Discussion:
Question #: 18
Topic #: 2

Which is a purpose of the 'directing a project' process?


A.

To exercise overall control over the project


B.

To take corrective action to control risks and issues


C.

To do the minimum in order to decide whether the project is feasible


D.

To update the project plan before the next stage