PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 3 Topic 1 Discussion

PRINCE2 7 Foundation written Exam Prince2-Foundation Question # 3 Topic 1 Discussion

Prince2-Foundation Exam Topic 1 Question 3 Discussion:
Question #: 3
Topic #: 1

Which is a purpose of the 'identify the risks' step within the recommended risk management procedure?


A.

To identify responses to risks documented in the business case


B.

To identify information about the project environment and objectives


C.

To identify the roles to be involved in risk management activities


D.

To identify uncertainties that may impact on the delivery of the project objectives


Get Premium Prince2-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.