PRINCE2-Agile-Foundation Exam Topic 3 Question 21 Discussion:
Question #: 21
Topic #: 3

During which process should release planning be done for the FIRST time?


A.

Initiating a project


B.

Managing a stage boundary


C.

Managing product delivery


D.

Controlling a stage