PRINCE2 Agile Foundation (Version 2) Exam PRINCE2-Agile-Foundation Question # 19 Topic 2 Discussion

PRINCE2 Agile Foundation (Version 2) Exam PRINCE2-Agile-Foundation Question # 19 Topic 2 Discussion

PRINCE2-Agile-Foundation Exam Topic 2 Question 19 Discussion:
Question #: 19
Topic #: 2

Which process can take place during a release review workshop?


A.

Controlling a stage


B.

Managing product delivery


C.

Managing a stage boundary


D.

Directing a project


Get Premium PRINCE2-Agile-Foundation Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.