PMP Exam Topic 63 Question 626 Discussion:
Question #: 626
Topic #: 63

During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team

How should the project manager handle this situation?


A.

Implement crashing to compress the schedule and improve the schedule performance index (SRI).


B.

Implement fast-tracking to compress the schedule and improve the SPI


C.

Perform conflict management using the project's resource management plan.


D.

Review the risk management plan to evaluate the probability and impact of these delays